Once the frames were ready we began to lift them into place. Again with Simon's experience of lifting and then bracing the structure as it was put into place the whole process of one long wall small back wall and other long wall took just half a day to be in place and secure.
The Front wall was then built with the other frames in position. Extra nogins, dwangs were added for strength so by the end of the day all the walls were up and braced and square.
Once up the frames were rejoined at the cut points. We then placed scaffold around the building to enable us to do the roof plates and frame before fitting the roof joists.